Personal Case Study: Tampa Port Authority Security Improvements

While Matt Wurthner was Vice President at Technology Services Inc @USF (TSI) his major duties included: Project Management, Operations Management, Security Design and Implementation.  TSI was a participant in a proposal by American Bridge Inc. (ABI) to provide a comprehensive security system for the Tampa Port Authority.  Subsequent to ABI being awarded the total contract, TSI@USF became a major subcontractor to ABI for the provision of communications infrastructure, security systems, and access control.   

The original scope of work from American Bridge was to be $4,753,796.50 and included the installation of equipment according to a design to be provided by a separate engineering firm.  American Bridge was not able to reach agreement with the engineering firm and asked TSI@USF to pick up the design elements for an additional $275,000.  Thus the total value of the contract with American Bridge is $5,028,796.50.

 

For a full description of the Case Study please download PDF.

 

 

 

 

 

 

 

 

 

 

Contact Us | Site Map